DR1801
Covington Woods Drainage Improvements - Sugar Land MS/Sugar Mill Relief Line
Project Phase
Construction
Design 100 %
 
Construction 100 %
 
$239,975.00
CO's ; Revenue Bonds
Jorge Alba
LAN, Inc.
Tommy Thompson
WadeCon LLC.
Design and construction of a new relief storm sewer outfall along the City-owned park adjacent to Sugar Land Middle School and the outfall to Ditch A-22. Project is designed to increase the capacity of the 7th Street storm sewer system.
Covington Woods is subject to wide spread roadway inundation during medium to extreme rain events. Many of the roadways are impassible during these storm events and subject to excessively long times to drain leading to decreased mobility. Portions of the area do not meet current City design standards. Improvements are needed to address these issues.
Quarterly Updates

FY20

4th Quarter Synposis (July 1 - September 30)

The Contractor has completed all items of the project including drainage improvements, water line replacement and street reconstruction along 7th street, Muirwood lane and the City owns park. Project has been closed.

1st Quarter Synposis (October 1 - December 31)

In early October 2019, the Contractor began construction of Phase 2 of the project, which included the replacement of the 7th Street pavement from W. Green Belt Dr. to Bournewood. During a field inspection, a design error was discovered. The design issue was resolved and the construction plans modified. The contractor resumed work on the segment of 7th Street, between W. Greenbelt Dr. and Bournewood.

FY19

4th Quarter Synposis (July 1 - September 30)

Phases IA and IB of the Project (Drainage and Street improvements from the City-owned Park to W. Green Belt) were completed on September 28, 2019. Phase II (westbound Segment of W. Green Belt to Bournewood and Muirwood Dr) construction started on September 26, 2019.

3rd Quarter Synposis (April 1 - June 30)

Project was bid in May 2019 and the Contractor was selected. The Contractor initiated the project on June 10, 2019 and began removing the north lane pavement along 7th St. between the City-owned park and West Green Belt. Installation of the stormwater line on 7th street and the park commenced as well.

2nd Quarter Synposis (January 1 - March 31)

Project design was completed and approved in February 2019. A project meeting was conducted at Sugar Land Middle School on February 25, 2019. The project was bid on March 28, 2019. All bids submitted were above budget. Project will be repackaged and rebid in May or June 2019.

1st Quarter Synposis (October 1 - December 31)

The consultant submitted construction drawings for review in December 2018. There is a Public Meeting at the Sugar Land Middle School scheduled for February 25, 2019. Final construction drawings are scheduled for February 2019.

FY18

4th Quarter Synposis (July 1 - September 30)

The consultant has completed the surveying of all utilities in the project area. Also, the schematic design of the stormwater line is complete. It has been determined that its necessary to acquire additional ROW to avoid placing water lines under the pavement. The Parks Department requested relocating the stormwater line inside the park property. A new alignment was decided and additional survey of the park and areas where ROW is necessary was completed.

3rd Quarter Synposis (April 1 - June 30)

Consultant is performing surveying of the project area, and determining the location of all utilities along 7th street between Eldridge and Wood St, Muirwood lane, Woodlake Circle and the Sugar Land City Park next to the Middle School.

2nd Quarter Synposis (January 1 - March 31)

Contract signed and NTP issued on 03/20/18. Kickoff meeting was held 03/23/18. Meetings with SL Middle School and HOA were held the week of 3/26/18.

1st Quarter Synposis (October 1 - December 31)

Final scope and fee is being negotiated with the Consultant.